Tell us what you're building and roughly how big it is. We'll tell you how many cubic yards to order, how many bags it'd take if you're doing it yourself, and whether it's a job worth handing off.
Concrete is sold by volume, not by weight or by area. That's the part that trips most people up. You don't order "a patio" — you order a number of cubic yards, which is just a way of measuring a 3-D chunk of space.
One cubic yard is a block 3 feet long, 3 feet wide and 3 feet tall. That's 27 cubic feet, and it weighs somewhere around two tons. So the math for a flat slab is:
length (ft) × width (ft) × thickness (ft) ÷ 27 = cubic yards
The only trick is that thickness is almost always given in inches, so you divide it by 12 first. A 4-inch slab is one-third of a foot. That's the whole secret — everything else on this page is just that same idea applied to different shapes.
Thickness is the number people guess at, and guessing thin is how slabs crack. These are common starting points, not code. Your building department and your soil have the final say.
| What you're pouring | Common thickness | Why |
|---|---|---|
| Walkway or sidewalk | 4 inches | Foot traffic only. |
| Patio | 4 inches | Go to 5 if you're putting a heavy grill, fire feature or hot tub on it later. |
| Driveway (cars) | 4–5 inches | 5–6 inches if trucks, RVs or trailers will park on it. |
| Garage or shop floor | 4–5 inches | Thicker at the edges is common. |
| Hot tub or spa pad | 6 inches | A full tub is thousands of pounds in a small footprint. |
| Shed or small outbuilding | 4 inches | Heavier buildings may need a thickened edge or piers. |
| AC or generator pad | 4 inches | Check the equipment manufacturer's spec. |
| Footings under a wall | Code-dependent | Do not guess this one. Width and depth come from your building department. |
This is the real decision, and it comes down to volume.
One cubic yard is about 45 eighty-pound bags, 60 sixty-pound bags, or 90 forty-pound bags. Yields vary a little by brand, so check the bag.
Most concrete guidance online is written for mild weather and quietly assumes you'll never see 110°F. Here, heat is the main variable. Hot concrete sets faster, which shortens your working time and raises the risk of surface cracking if it dries before it cures. Summer pours in the valley commonly get scheduled early in the morning for exactly this reason, and there are established practices for hot-weather placement and curing. This is worth a conversation with your supplier or contractor rather than a rule of thumb from a website — including ours.
Cement is one ingredient. Concrete is the finished mix: cement plus water plus sand and gravel. Asking for "cement" when you mean a slab is like asking for flour when you want a cake.
5 to 10 percent over your calculated volume. It covers spillage, a subgrade that's slightly deeper than you thought, and the fact that nobody digs a perfectly flat hole. Ordering short means either a second delivery fee or a cold joint in your slab.
Walking, generally 24 to 48 hours. Driving, around 7 days. Concrete keeps gaining strength for weeks and is typically considered fully cured at 28 days. Heat and mix design shift all of these, so follow what your supplier tells you for your specific pour.
No — reinforcement doesn't meaningfully change the volume. It changes how the slab behaves when the ground moves under it, which is a different and equally important question.
Usually the waste allowance. Some calculators give you the raw geometric volume with nothing added; we show you both the bare number and the number we'd actually order. Check whether the other tool included overage before assuming one of them is wrong.
For budgeting, yes. For building, no. Footing and stem wall dimensions are set by your local building code, your soil, and the load above them. Use this to estimate cost, then get the actual dimensions from your building department or engineer.